Factbox: Philippines Starts LNG imports, More Projects in Pipeline
05.24.2023 By TankTerminals.com News - NEWS

May 24, 2023 [Intraksyon]- With just four more years to go before the Philippines‘ only gas field might halt production, the country has started importing liquefied natural gas (LNG), adding upward pressure to already worryingly high inflation.

 

Seven terminal projects have been approved by the Philippines‘ Department of Energy, as it looks to expand LNG usage into industrial, commercial, residential and transport sectors in addition to power.

Following are the project proponents and their partners, proposed capacities, timetable and status as of April 24, according to the energy department.

PHLNG import terminal

(previously Atlantic Gulf & Pacific Co of Manila Inc)

Partner: Osaka Gas Co Ltd 9532.T, which has technical services agreement with AG&P

Description: Floating Storage Unit and Onshore Regasification, and buffer LNG storage tank

Location: Batangas City

Capacity: 3 million tonnes per annum (mtpa)

Estimated Commercial Operations Date (COD): FSU and Onshore Regasification in May 2023, and buffer LNG storage tank in December 2023

Status: LNG cargo from trader Vitol has arrived and will fuel San Miguel Corp’s SMC.PS 1,200-megawatt power plant in Batangas, which is scheduled to come online by May 26

FGEN LNG of First Gen Corp FGEN.PS

Partner: Tokyo Gas Co Ltd 9531.T, which has a 20% interest

Description: Floating Storage and Regasification Unit (FSRU)

Location: Batangas City

Capacity: 5.26 mtpa

Estimated COD: September 2023

Status: Commissioning scheduled in third quarter

Energy world gas operations Philippines Inc.

Proponent: Energy World Corp Ltd EWC.AX

Description: LNG Storage and Regasification Terminal

Location: Pagbilao Grande Island, Quezon Province

Capacity: 3 mtpa

Estimated COD: December 2023

Status: Permit to construct extended for 1 year and issued on Jan. 31, 2023

Shell energy Philippines Inc. 

Proponent: Shell Pilipinas Corp SHLPH.PS

Description: FSRU

Location: Batangas City

Capacity: 3 mtpa

Estimated COD: September 2025

Status: 20-month extension of Notice To Proceed issued in January 2023

Luzon LNG Terminal Inc. 

Description: FSRU

Location: Batangas Bay

Capacity: 4.4 mtpa

Estimated COD: December 2025

Status: Permit to Construct issued in December 2022

Vires Energy Corp

Description: FSRU

Location: Batangas City

Capacity: 3 mtpa

Estimated COD: September 2025

Status: 2-year extension of Notice To Proceed issued and valid until October 2023

Samat LNG Corp

Description: Small-Scale LNG Terminal

Location: Mariveles, Bataan

Capacity: 0.32 mtpa

Estimated COD: Phase 1 in March 2024, Phase 2 in May 2025

Status: Notice To Proceed issued in January 2023

Pro Trial: Access 12,600 Tank Terminal and Production Facilities

12,600 tank storage and production facilities as per the date of this article. Click on the button and register to get instant access to actionable tank storage industry data

10-year Treasury yield hovers close to highest level since April as investors await key jobs data
01.10.2025 - NEWS
U.S. Treasury yields hovered close to its highest level since April on Friday, as investo... Read More
Union dockworkers, port employers announce tentative deal at East Coast and Gulf ports
01.09.2025 - NEWS
State of Freight The tentative agreement is on all items for a new six-year mas... Read More
China's property market is expected to stabilize in 2025 — but stay subdued for years
10.30.2024 - NEWS
China’s struggling real estate sector may not start turning around until the sec... Read More
Harris will offer an alternative to Trump-era politics in closing argument speech
10.29.2024 - NEWS
1234534234 Democratic presidential nominee U.S. Vice President Kamala Harris walks to bo... Read More