Venice Energy Nears FID on South Australian LNG Import Project
09.06.2023 By Tank Terminals - NEWS

September 6, 2023 [LNG Prime]- Venice Energy expects to take a final investment decision to build its FSRU-based LNG import project in the Port of Adelaide, South Australia, by early October, according to the company’s managing director, Kym Winter-Dewhirst.

 

Earlier this year, Venice Energy estimated it could reach FID on the proposed LNG terminal in the Outer Harbor by the end of August.

Winter-Dewhirst told LNG Prime on Tuesday that the project team “has made significant progress towards that goal but at this stage we now believe FID will more likely be reached by the end of September or early October.”

“If we achieve this major milestone we will begin site enabling works, as the first stage of the project, by November. This will be the start of a 24 month construction phase that will see the FSRU with a first cargo of LNG arrive in Adelaide by December 2025,” he said.

Winter-Dewhirst added that the company is in the “final stages of customer negotiations and expects this phase to be settled very soon to then allow us to move to FID, followed by commercial close.”

 

GasLog to convert LNG carrier to FSRU

Last year, Japanese trading and investment house, Marubeni, has signed a memorandum of understanding with Venice Energy to join the latter’s FSRU-based LNG import project.

Venice Energy said at that time that as part of the deal with Marubeni it would create a joint venture partnership for its A$260 million ($166 million) project under development in South Australia.

The terminal will include the development of two berths in the Outer Harbor channel, along with the FSRU, cryogenic piping, as well as associated infrastructure.

Venice Energy claims the LNG terminal will be the first in the world to operate exclusively on renewable energy.

The company signed a heads of agreement with Greece’s GasLog in July 2021, under which the latter would supply an FSRU for the project.

In January this year, Paolo Enoizi, CEO of Greek LNG shipping firm GasLog said that company has agreed in principle to convert one of its 145,000-cbm steam LNG carriers to an FSRU and charter it to Venice Energy.

“Such conversion is expected to cost in excess of $100 million and take between eight to 10 months,” Enoizi said.

 

Pro Trial: Access 12,600 Tank Terminal and Production Facilities

12,600 tank storage and production facilities as per the date of this article. Click on the button and register to get instant access to actionable tank storage industry data

10-year Treasury yield hovers close to highest level since April as investors await key jobs data
01.10.2025 - NEWS
U.S. Treasury yields hovered close to its highest level since April on Friday, as investo... Read More
Union dockworkers, port employers announce tentative deal at East Coast and Gulf ports
01.09.2025 - NEWS
State of Freight The tentative agreement is on all items for a new six-year mas... Read More
China's property market is expected to stabilize in 2025 — but stay subdued for years
10.30.2024 - NEWS
China’s struggling real estate sector may not start turning around until the sec... Read More
Harris will offer an alternative to Trump-era politics in closing argument speech
10.29.2024 - NEWS
1234534234 Democratic presidential nominee U.S. Vice President Kamala Harris walks to bo... Read More