PSO Seeks to Build Storages, Connect Ports Via Pipeline
08.24.2016 - NEWS

August 24, 2016 [The Express Tribune] - In a bid to ensure energy security of the country, state-run oil marketing company Pakistan State Oil (PSO) has asked the government to allow the building of more storages and a pipeline to connect Karachi Port and Port Bin Qasim for streamlining the supply of petroleum products.


“A plan has been sent to the federal government, seeking go-ahead for constructing new oil storage facilities and connecting the two ports in Karachi through a pipeline,” said a senior PSO official while talking to The Express Tribune.

“The economy and energy security of Pakistan heavily depend on regular and sustainable supplies of imported fuels.”

At present, the annual demand for petroleum products stands at around 23 million tons in the country and it is expected to touch 27 million tons by 2020.

Of the total volume, the demand for 10 million tons, or 44%, is met by domestic refineries whereas 13 million tons (56%) are imported.

More than two-thirds of the crude processed by local refineries is brought through imports. In financial year 2015, the refineries processed around 3.9 million tons (32%) of crude oil produced in the country and 8.2 million tons (68%) of imported oil.

PSO – the largest oil marketing company – meets energy needs of the country through a wide network of depots with a storage capacity of around one million tons, which constitutes around two-thirds of the storage capacity of all oil marketing companies.

The demand for premier motor gasoline (PMG) has shown unprecedented growth over the past many years in the country, which has increased five times from 1.15 million tons in financial year 2007 to 5.8 million tons in 2016.

Of the total PMG demand, only 1.6 million tons (28%) is produced in the country whereas 4.2 million tons (72%) are imported and handled at terminals at Karachi Port.

However, according to the official, it has become extremely difficult for PSO to smoothly meet the demand and swiftly offload PMG from vessels carrying 50,000 tons or more because of lack of storages at the port. The current storage capacity is only 40,000 tons at Keamari, Karachi Port.

Moreover, due to jetty constraints at Port Qasim, the transport of PMG from Keamari to Port Qasim is also difficult.

In this scenario, he said, the supply chain of PMG and other fuels was increasingly at risk due to delay and crowding of vessels.

In an effort to tackle storage constraints which also led to the petrol crisis in January 2015, the Ministry of Petroleum and Natural Resources had asked PSO to enhance the PMG storage capacity to 150,000 tons – 100,000 tons in Karachi and 50,000 tons in the upcountry.

In response, PSO prepared a plan in July 2015 for enhancing the storage capacity to about 125,000 tons.

It asked the Ministry of Industries and Production to allow conversion of all non-dangerous product/heavy product storage tanks at Keamari Terminal-C (40,000 tons) into dangerous product tanks for storing PMG. Its approval has been received in two cases and another two are being reviewed.

10-year Treasury yield hovers close to highest level since April as investors await key jobs data
01.10.2025 - NEWS
U.S. Treasury yields hovered close to its highest level since April on Friday, as investo... Read More
Union dockworkers, port employers announce tentative deal at East Coast and Gulf ports
01.09.2025 - NEWS
State of Freight The tentative agreement is on all items for a new six-year mas... Read More
China's property market is expected to stabilize in 2025 — but stay subdued for years
10.30.2024 - NEWS
China’s struggling real estate sector may not start turning around until the sec... Read More
Harris will offer an alternative to Trump-era politics in closing argument speech
10.29.2024 - NEWS
1234534234 Democratic presidential nominee U.S. Vice President Kamala Harris walks to bo... Read More